As on 16.04.2015 excavation and blasting works have been executed at the tunnel entrance in the amount of 73 000 m3 from 73000 m3 (100%). At the tunnel exit 56 000 m3 of soil have been excavated from 56 000m3 (100%). At the acces adit 10 000 m3 of soil (as in design solution) have been excavated from 10 000m3 (100%).
55566 m3 of Tunnel excavation have been carried out by underground method. Right side is 321,05 m, left side is 299 m, acces adit is 60 m. Total the rock have been excavated for 680,05m from 1490m (42%). Shotcreting have been made in the amount of 6395 m3. Totally 308 items of lattice have been installed. 15330 m2 of mesh and 4560 pm of rock bolt have been installed to strengthen the tunnel crown.
Tunnel second working has been begun (Bench). 286 m has been executed.
Furthermore work on foundation concreting for Lining (reinforced concrete support, 30 cm thick) has been begun at the tunnel inlet. 95m3 concrete have been done.
The following road building machnery was involved:
Mobile form has been obtained for the tunnel crown concreting.
120 people work in the tunnel – 36 foreign and 84 local staff.
State Expertise Conclusion No. 01-0646 dated October 20, 2014 has been obtained.
The list of tasks according to work plan for 2015:
Excavation of the main tunnel will be completed up to 25.07.2015.
Inlet portal
Outlet portal
Furnishing of the tunnel will be made up to 01.12.2015