Currently, the reconstruction works are carried out along the entire Taldykorgan – Kalbatau-Ust-Kamenogorsk road. The works are performed by the construction consortium Todini Central Asia LLP, K-Dorstroi JSC, CITIC Construction Co, and LTD (Leaderin Consortium).

So, the road workers constructed Bypasses, more than 1,000 m3 of the Earthworks and 50 nos. of Culverts on the road section from km 615 to 1073.

In addition, this year the road workers will complete 26.7 km of subgrade, 21 km of C-4 crushed-sand mixture subbase course, and 13 km of binder and asphalt courses.

The main purpose of the road reconstruction is to change the road Category from III to II, by widening carriageway up to 9 meters where the speed limit will be up to 120 km/h to ensure safe and uninterrupted traffic.

It should be noted that the construction of the road will lead to economic growth in the region and related areas.

 

 

 

«Важное значение имеет завершение строительства казах-
-станского участка международ-
-ного автомобильного коридора «Западная Европа - Западный Китай». Это действительно народная стройка века. Где еще за три года было построено 2700 км. качественной автомобильной дороги? Мы должны в следующем году эту работу закончить»
 
 
(Из Послания Президента Республики Казахстан – Лидера Нации Н.А.Назарбаева народу Казахстана "Социально-экономическая модерни-
-зация – главный вектор развития Казахстана».  Январь 2012 года)

 

 

 

 

 

 

 

 

Выставка КазАвтоДор 2015

 

 

Проекты "ЗЕ-ЗК"
Проекты "Нурлы жол"
Закупки
Объявления
Пресс-центр
Мультимедиа
Вопросы и ответы Контакты