Overall length of the road section, Lot 3, where company “Copri/Seiser ’ works at present, is 24 km. As per status for May 13, 2011, overall mobilized are as follows : personnel – 251 people, including international – 13 people; equipment - 79 units, 3 of which belong to the Subcontractor. Under the Project the following objects will be built at the road section : 3 bridges and 3 overpasses for the road section “Staryi Ikan village By -pass”. The road is of the first category.
As Rustam Kassymov, Deputy Supervision Engineer of “Kazdorproject” LLP, tells, in the current year the Contractor plans to construct 15 km of the road . Surfacing will be cement concrete one. Contractor’s and Engineer’s Service offices are located in the same building. It is very convenient for operative settlement for one or anothe r matter regarding construction . The Contractor intends to perform all construction erection works at the road section with total length of 24 km himself. Subcontractor “Svyazmontazhstroi” has been inv olved in works only for relocation of communication lines.
The Contractor will install his own crusher, cement concrete plant. If Contractor completely is on schedule, the old road will be milled to the end of September of the current year.
Maintenance of the road is also under control. All the required road signs are installed, including signs for speed limit. Watering is regularly carried out.
Interview with Rustam Kassymov, Deputy Supervision Engineer of “Kazdorproject” LLP – Construction Supervision Consultant – has been published in the Section “Press-center” (Articles and interviews) of this website.