The results of analysis or mobilization of the road-building equipment for South-Kazakhstan section of the Corridor “Western Europe – Western China” showed that plan implementation is 79%.

Completion of overall mobilization for road-building equipment for South-Kazakhstan section was planned to the end of July 2011. However, out of total required amount for 1241 units, only 979 units are available, which undoubtedly influenced over common outline for execution of timing schedules.

So, as per status for August 22, 2011, CJSC “Dena Rahsaz”, instead of prescribed 269 units of equipment, has mobilized only 221 units. South-Korean company “Posco” needs 65 units of equipment more, including dozers, graders and other machinery.

Contractor JV “Copri/Seiser” does not have sufficient number of dumpers. Overall the company should mobilize more than 20 units of equipment of various applications.
Azerbaidjan-Turkey Joint Venture “Azerkorpu/Tepe”, executing construction of Sairam section in South-Kazakhstan Oblast, is expecting the arrival of the large number of dumpers, experiencing acute shortage, which is connected with the construction of a large-scale interchange.

Chinese company “Sinohydro” has such type of equipment in redundant number, which instead of calculated 53 units has mobilized 85 units. However, because of lack of organization of the managing staff there are frustrations of timing schedules.

Korean company “Kukdong” is in problem situation with mobilization of equipment. Only one third of the required number of dumpers has been involved in its sites. There is also insufficient number of other machinery. That is, plan for mobilization has been executed just for 38.8%. Today the company has a new Project Manager, who makes his own corrections for management in construction.

 

 

 

 

«Важное значение имеет завершение строительства казахстанского участка международного автомобильного коридора «Западная Европа - Западный Китай». Это действительно народная стройка века».
«Мы ставили задачу развивать инфраструктуру. И это оказалось нам по силам. В настоящее время мы возрождаем Новый Шелковый путь. Мы открыли доступ к странам Персидского залива и Большого Востока. Мы распахнули восточные ворота, проложив путь на рынки Китая и всего Азиатского континента». «Стратегия «Казахстан-2050».
 
 
Послание Первого Президента РК - Елбасы, 2012 г.

 

 

 

 

«Исполнительной власти нужна полная, качественная программа «Нурлы Жол». Это стратегический проект, благодаря которой будет затронута вся транспортная инфраструктура».

 

 

 

 

Стратегия 2050

 

 

 

 

Проекты "ЗЕ-ЗК"
Проекты "Нурлы жол"
Закупки
Объявления
Пресс-центр
Мультимедиа
Вопросы и ответы Контакты