Shymkent-Tashkent project work progress

At the moment, «Sinohydro Corporation Limited», General Contractor of the first section of the abovementioned project, received approval for subcontracting "Kazvodenergostroy" LLP for Dismantling bridges and also it plans to attract subcontractors for earthworks.

The Laboratory of the Contractor is equipped for 100% and it corresponds to the requirements of technical specifications.

With respect to the production base completed the installation of the cement concrete plant is being carried out – 2 nos. with the capacity 250 tns/hour each. The installation of mixing plant for CSSCM production is done, Silos for cement with the capacity of 2100tns is at the site, track scales are installed.

As of today the following works performed: milling of 2.3 km out of 36 km according to the plan for 2015; culverts - 0.5 pc out of 45 pc according to plan for 2015; bridges and overpasses - 0.2 pc out of 5 pcs. According to the plan for 2015.

From the beginning of the year procurement of main road-building materials contains: crushed stone - 37.27 thousand. m3; sand - 5.52 thousand. m3; concrete - 1.17 thousand. m3; cement - 0.13 thousand. tn.

Concerning the involvement of staff out of 283 people required for 2015, 125 people have been mobilized. Regarding equipment mobilization out of 194 pieces of equipment required for 2015 a total of 64 pieces of equipment have been mobilized.

To date, "Evrascon" Euro-Asian Construction Corporation, General Contractor of the second section, has signed a contract with Subcontractor «Shyrak-LKS» for reconstruction of communication lines and "KazTsEP" LLP for relocation and Reconstruction of power transmission lines, reconstruction of pipeline medium and high pressure. Both Subcontractors has commenced preparatory work on the removal of communication and power lines, respectively. Also it is planned to attract Subcontractors for reconstruction of gas pipeline BGR-TBA, "Dani-Er" LLP is presented to the Engineer’s approval.

There is being carried out negotiations on registration of suppliers of building and inert materials. From the beginning of the year  procurement of main road-building materials contains: crushed stone - 3.2 thousand. m3; SGM - 2.8 thousand. m3; sand - 0.8 thousand. m3; concrete - 0.32 thousand. m3; cement - 0,006 thousand. tn.

Mainly earthworks are being conducted from the planned volume for 2015 in the amount of 512, 57 thousand. m3 at the moment 2.87 thousand. m3 implemented.

Concerning the involvement of staff out of 386 people required for 2015, 115 people have been mobilized. Regarding equipment mobilization out of 235 pieces of equipment required for 2015 a total of 58 pieces of equipment have been mobilized.

 

 

 

«Важное значение имеет завершение строительства казахстанского участка международного автомобильного коридора «Западная Европа - Западный Китай». Это действительно народная стройка века».
«Мы ставили задачу развивать инфраструктуру. И это оказалось нам по силам. В настоящее время мы возрождаем Новый Шелковый путь. Мы открыли доступ к странам Персидского залива и Большого Востока. Мы распахнули восточные ворота, проложив путь на рынки Китая и всего Азиатского континента». «Стратегия «Казахстан-2050».
 
 
Послание Первого Президента РК - Елбасы, 2012 г.

 

 

 

 

«Исполнительной власти нужна полная, качественная программа «Нурлы Жол». Это стратегический проект, благодаря которой будет затронута вся транспортная инфраструктура».

 

 

 

 

Стратегия 2050

 

 

 

 

Проекты "ЗЕ-ЗК"
Проекты "Нурлы жол"
Закупки
Объявления
Пресс-центр
Мультимедиа
Вопросы и ответы Контакты