How do you do! I am interested in receiving reply to the following questions.
How many bridges are planned to be constructed for 2014-2015 under this project? What is their length and who is the Contractor? Where can I obtain such information?
Thank you in advance.
Dear Vladimir, according to the following table you can see how many artificial structures will be built on the remaining sections of Western Europe – Western China (WE-WC) project in 2014-2015.
No.
|
Project name
|
Section
|
Quantity (pcs.)
|
Contractor
|
1
|
South-West Roads Project: WE-WC; Section in Kyzylorda oblast
|
km 1702- 1752
|
12 bridges,
1 overpass
|
“Evrascon” JSC (Azerbaijan)
|
2
|
‘Shymkent-border of Zhambyl oblast”
|
km 593-632
km 632-674
|
3 bridges,
4 overpasses,
3 bridges, 7 overpasses,
2 cattle crossings
|
JV “Dena Rahsaz” (Iran) & “Sargin” (Turkey)
Sinohydro Corporation Limited (China)
|
3
|
“Almaty-Khorgos”
|
km 0-171,1
km 171,1-304,4
Bridges and overpasses on km 214,3-304,4
Ili Bridge (km 283)
|
29 bridges, 23 overpasses
4 bridges, 2 overpasses
23 bridges, 8 overpasses
|
«Dogus Insaat» & «Gulsan Insaat» (Turkey/Turkey)
JV Todini-Impregilo
-Kazakhdorstroy (Italy/ RK)
JV “Evrascon” (Azerbaijan) & “MO-1” (Kazakhstan)
“OHL ZS” (Czech Republic)
|