How do you do! I am interested in receiving reply to the following questions.
How many bridges are planned to be constructed for 2014-2015 under this project? What is their length and who is the Contractor? Where can I obtain such information?
Thank you in advance.
How many bridges are planned to be constructed for 2014-2015 under this project? What is their length and who is the Contractor? Where can I obtain such information?
Thank you in advance.
Answer to question №268
Dear Vladimir, according to the following table you can see how many artificial structures will be built on the remaining sections of Western Europe – Western China (WE-WC) project in 2014-2015.
No.
|
Project name
|
Section
|
Quantity (pcs.)
|
Contractor
|
---|---|---|---|---|
1
|
South-West Roads Project: WE-WC; Section in Kyzylorda oblast
|
km 1702- 1752
|
12 bridges,
1 overpass |
“Evrascon” JSC (Azerbaijan)
|
2
|
‘Shymkent-border of Zhambyl oblast”
|
km 593-632
km 632-674
|
3 bridges,
4 overpasses, 3 bridges, 7 overpasses,
2 cattle crossings |
JV “Dena Rahsaz” (Iran) & “Sargin” (Turkey)
Sinohydro Corporation Limited (China)
|
3
|
“Almaty-Khorgos”
|
km 0-171,1
km 171,1-304,4
Bridges and overpasses on km 214,3-304,4
Ili Bridge (km 283)
|
29 bridges, 23 overpasses
4 bridges, 2 overpasses
23 bridges, 8 overpasses
|
«Dogus Insaat» & «Gulsan Insaat» (Turkey/Turkey)
JV Todini-Impregilo
-Kazakhdorstroy (Italy/ RK) JV “Evrascon” (Azerbaijan) & “MO-1” (Kazakhstan)
“OHL ZS” (Czech Republic)
|