Question №471
February 2, 2017
Maxim Krivonossov | Almaty region

Good day! I have written you earlier on the construction of Uzynagash-Otar section. As far as I know, the signing of loan agreement with the World Bank and conducting of tender procedures has been scheduled for the 2nd half of 2016. Also in December 2016 applications from contractors were accepted to participate in tender. Could you please reply what has been done to date for the commencement of construction work at the site? And please indicate the date when it is scheduled to start? In March 2017, or ...? When will the staff be formed?

Answer to question №471
February 24, 2017

Dear Maxim, in coordination with the World Bank, tender procedures were announced in October 14, 2016; in November 14, 2016 companies submitted their application for pre-qualification. Currently, in accordance with the procedures of the World Bank assessment and approval of the results of prequalification is being carried out. Prequalified companies will be invited to submit their bid in the second quarter of 2017. The signing of the contract and the start of the project is planned after attracting funds to be received after the ratification of the Loan Agreement tentatively in the third quarter of 2017.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts