- I would like to clarify something regarding condition of the highway “Almaty – Astana”. At the exit from Almaty 100 km are more or less good. As for the rest of 250 km you can say that there is not any road at all, pit after pit. But they reported to the President of our country, Nursultan Abishevich, that the highway of international importance, Astana – Almaty, has entirely been completed. What does it mean?

Answer to question №169
March 12, 2013

Dear Esenkul! The length of the highway “Astana – Almaty” is 1 222 km, for 969 km of which reconstruction has been carried out for 1997-2003.

Due to the lack of finance to provide traffic safety for the road section Kurty – Burylbaital with the length of 223 km the repair-renewal operations have been carried out with finishing of pavement up to satisfactory condition.

In accordance with the Program for Development of Transport Infrastructure of the Republic of Kazakhstan for 2010-2014 reconstruction of the above road section has been planned to commence in 2014. The development of all the design-estimate documents will be completed and they will be approved in 2013. Technical condition of the highway till carrying-out of the reconstruction will be provided by means of periodical repair works.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts