Question №257
September 22, 2013
Aidar Danebayev | Zhambyl oblast, Kordai raion

I own the land plot along the constructed "Western China - Western Europe" highway close to Kainar (Blagoveschenka) at Kordai -Shu-Taraz-Almaty junction. The intended use is to maintain the farm.
However, due to the fact that this land is not suitable for irrigation, I intend to change its intended use and build there roadside service point of the "C" class.
In this regard, will I be given the permission for the construction of roadside service point on my plot along the "Western China - Western Europe" highway?
How and where do I need to obtain the permission and approval for entrance and exit to my plot from the highway? What documents and where do I need to submit them for this purpose?
How, at whose expense, and by whose force shall be laid roadbed for entrance and exit to the plot?
Is it true that a moratorium for the construction of a private roadside service points along the constructed "Western China - Western Europe" highway has been declared?
My friends told me that my intentions are ineffective, because the exit to the highway will be closed by special guardrails, and that it is almost impossible to get permisiion and approval for construction since it is not provided by the project design.
Is it really indeed?
Please kindly provide me with detailed answers to each of these questions.

Answer to question №257
October 16, 2013

Dear Aidar, for the construction of a roadside service object on your land plot you have to change the intended purpose of this plot in accordance with Article 49-1 of the Land Code of the Republic of Kazakhstan. In order to receive approval for exit construction to the roadside service object you should contact the Road agencies and provide necessary documents for this procedure in accordance with item 23-3 of the "Rules for the use of roads in the Republic of Kazakhstan" approved by the Government of the Republic of Kazakhstan on September 5, 1998 № 845 "About improving of the legal provision of road infrastructure".

Regarding the acceleration and deceleration lanes to the object due to the fact that "Western Europe - Western China" International Transport Corridor road (hereinafter - "WE - WC") is the road of the 1st technical category, in accordance with item 6.3.1 of "SNIP RK 3.03-09-2006 HIGHWAYS” at exits to the buildings and to the constructions of roadside service the acceleration and deceleration lanes in each direction should be provided. Moreover, in accordance with item 5 of Article 8 of the Law "About highways" the cost for the arrangement, repair and maintenance of entrances (exits, junctions) is under responsibility of the owners of these objects.

As for the barriers, the corridor road passing through Zhambyl oblast is not equipped with curved bars. Moreover, there are no restrictions on construction of new objects except for cases affecting the road safety.

In addition, in view of the completion of "WE-WC" a moratorium on the construction of the roadsie service objects does not cover.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts