Dena Rahsaz/Sargin JV is constructing the road section between km 593 to km 632 consisting of 40 km road and 800 m of tunnel.
And according to the Engineer «Temelsu» in association with «Consult Ltd» LLP it is planned to complete construction of tunnel at the end of 2016.
State Expertise conclusion has been received under №01-0646/14 dated 20 October 2014.
To date the following works have been performed:
Drilled (along chainage):
Concrete placed (crown):
Shotcrete was constructed in the volume of 7600 m3. Overall 2650 pcs. of supports, 48 500 m2 of grid, 10000 rm of auxiliary bars for strengthening of crown were installed.
The following road building machinery and equipment is involved in the construction of tunnel:
30 people, including 5 foreign and 25 local staff are working in the construction of tunnel.