Home > Press-centre > News > Reconstruction Progress on Aktobe-Atyrau-border of the Russian Federation (to Astrakhan) Road km 833-893
News
Printer-friendly versionPrinter-friendly version
09/20/2019 
Reconstruction Progress on Aktobe-Atyrau-border of the Russian Federation (to Astrakhan) Road km 833-893

Photo: http://www.kazautozhol.kz

Currently, on km 833-893 section of Aktobe-Atyrau-border of the Russian Federation (to Astrakhan) the culverts are being constructed and gas pipeline and underground utilities are being relocated.

To date, 8 km of the lower base layer from a soil-mineral mixture have been completed, 7 km of the sand and crushed stone base course, and 4 km of the coarse asphalt concrete wearing course. Construction works are carried out by line process on pavement courses.

35.7 km of bypass road is open for traffic. In addition, the road workers keep on constructing RMD, including constructing foundations, walls, floors and roofs.

Totally, more than 250 people and about 180 units of equipment are involved and mobilized in the works on 60-kilometer road section.

 

 

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the international motor road corridor “Western Europe – Western China” is very important. It is really the construction of the century. Where else have 2,700 kilometres of quality motor road been built in three years? We need to finish the job next year».
 
 
(From Address by the President of the Republic of Kazakhstan Nursultan Nazarbayev to the People of Kazakhstan. 27.01.2012)

 

 

 

 

 

 

 

 

 