In the current year building company “Copri/Seiser” plans to construct 15 km out of 24 km of the overall length of the road section in South-Kazakhstan Oblast.

 Overall length of the road section, Lot 3, where company “Copri/Seiser ’ works at present, is 24 km. As per status for May 13, 2011, overall mobilized are as follows : personnel – 251 people, including international – 13 people; equipment - 79 units, 3 of which belong to the Subcontractor. Under the Project the following objects will be built at the road section : 3 bridges and 3 overpasses for the road section “Staryi Ikan village By -pass”. The road is of the first category.

As Rustam Kassymov, Deputy Supervision Engineer of “Kazdorproject” LLP, tells, in the current year the Contractor plans to construct 15 km of the road . Surfacing will be cement concrete one. Contractor’s and Engineer’s Service offices are located in the same building. It is very convenient for operative settlement for one or anothe r matter regarding construction . The Contractor intends to perform all construction erection works at the road section with total length of 24 km himself. Subcontractor “Svyazmontazhstroi” has been inv olved in works only for relocation of communication lines.

The Contractor will install his own crusher, cement concrete plant. If Contractor completely is on schedule, the old road will be milled to the end of September of the current year.

Maintenance of the road is also under control. All the required road signs are installed, including signs for speed limit. Watering is regularly carried out.

Interview with Rustam Kassymov, Deputy Supervision Engineer of “Kazdorproject” LLP – Construction Supervision Consultant – has been published in the Section “Press-center” (Articles and interviews) of this website.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts