08/22/2011 
The results of analysis or mobilization of the road-building equipment for South-Kazakhstan section of the Corridor “Western Europe – Western China” showed that plan implementation is 79%.

Completion of overall mobilization for road-building equipment for South-Kazakhstan section was planned to the end of July 2011. However, out of total required amount for 1241 units, only 979 units are available, which undoubtedly influenced over common outline for execution of timing schedules.

So, as per status for August 22, 2011, CJSC “Dena Rahsaz”, instead of prescribed 269 units of equipment, has mobilized only 221 units. South-Korean company “Posco” needs 65 units of equipment more, including dozers, graders and other machinery.

Contractor JV “Copri/Seiser” does not have sufficient number of dumpers. Overall the company should mobilize more than 20 units of equipment of various applications.
Azerbaidjan-Turkey Joint Venture “Azerkorpu/Tepe”, executing construction of Sairam section in South-Kazakhstan Oblast, is expecting the arrival of the large number of dumpers, experiencing acute shortage, which is connected with the construction of a large-scale interchange.

Chinese company “Sinohydro” has such type of equipment in redundant number, which instead of calculated 53 units has mobilized 85 units. However, because of lack of organization of the managing staff there are frustrations of timing schedules.

Korean company “Kukdong” is in problem situation with mobilization of equipment. Only one third of the required number of dumpers has been involved in its sites. There is also insufficient number of other machinery. That is, plan for mobilization has been executed just for 38.8%. Today the company has a new Project Manager, who makes his own corrections for management in construction.

 

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts