Reimbursement in 2012 was – 4 651.96 million tenge. Stationary crusher with capacity of 200 tons/hour, cement plant and mixer for production of base were additionally put into operation in January-March during the past year. At present 3 teams for installment of culverts and 3 teams for bridge construction have been organized. Also, two Subcontractors “Consulting” LLP and “UgRegionStroi” LLP have been additionally involved in construction of subgrade. Specialists from Macedonia carry out the works for construction of cement concrete pavement. Specialists of the manufacturing plant «Gomako» USA have been involved. The works have been carried out in two shifts for all road sections.
In the beginning of construction season 2012 there were some minor backlogs of schedule due to the late start of construction season nearly for a month because of weather conditions. Due to the Due to the overwetting for a period from 03.04.2012 to 15.06.2012 planned quantities have been revised for laying of subgrade, subbase and base course.
4 Subcontractors carried out the construction works for this road section up to the end of the year. Overall 304 units of equipment and machinery have been mobilized with target 230 units. Overall number of the personnel, involved in the contract, is 821 people, including international staff - 15 people. Other 806 people are citizens of the Republic of Kazakhstan.