At present this company procures road-building materials: gravel sand mix, crushed stone and sand, required for proceeding of road works in the forthcoming season for Lot 7 (2231-674 km) “Shymkent By-Pass Road” of International Transit Corridor “Western Europe – Western China”. Total length of the road section is 36.5 km (73 km in both directions). 40.2 km have been completed with cement concrete pavement in one direction in 2011-2012.
Overall 267 units of equipment and 647 people of the staff have been mobilized by the end of 2012. All proper conditions have been established for living and work of the staff. Contractor has 218 units of his own equipment. 3 plants for production of concrete, 2 crushers and laboratory fully equipped with the required technique are in operation on the territory of the site.
Some delays for bridge construction, which occurred by the end of 2012, has been eliminated. At present the works are in progress. As per status for February of the current year there are no debts for salary and for Subcontractors. The Contractor promises to complete overall construction of the road section in time, speeding up the pace for bridge construction in the current year.