Home > Press-centre > News > As a result of serious non-solved problems for LOT 4 of Kyzylorda Oblast there is a frustration of Work Schedule for 2013
News
Printer-friendly versionPrinter-friendly version
06/18/2013 
As a result of serious non-solved problems for LOT 4 of Kyzylorda Oblast there is a frustration of Work Schedule for 2013

Contractor, JSC «Salini Costruttori S.p.A», which executes civil works for Lot 4 of Kyzylorda Oblast, with target of 488.81 thousand tons for 2013, at present has procured 3.47 thousand tons of crushed stone, which means nearly nothing. Similar situation has occurred with procurement of cellular additive for crushed stone mastic asphalt.

To perform Work schedule for 2013 it has been required to mobilize 233 units of equipment. At present actual number of the equipment involved are only 122 units.

The Engineer finds the cause for low pace for arrangement of asphalt concrete mix at the site in frequent incapacitation of asphalt concrete plant of Chinese production, belonging to Subcontractor “Zhylyoistroiservice” LLP, mantled in the second half of the year 2011. Mix has been delivered from Lot 3.

To solve all the above problems Engineer’s Service finds it necessary to take measures as follows: start immediately supplying of inert materials and bitumen, establish two-shift regime of work and additionally involve Subcontractors to speed up the quantities of the executed works.

Reference: JSC «Salini Costruttori S.p.A» executes the works for km 1498-1578 (LOT 4) of Kyzylorda Oblast with the length of 80 km within Western Europe – Western China International Transit Corridor Project. Engineer: Isan Corporation/Zhol-Sapa LLP. With total Contract Amount of 12 644 918 608.2 tenge 6.642 billion tenge have been disbursed in 2010- 2012. Amount for works for 2013 is 7.410 billion tenge.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts