Home > Press-centre > News > Commencement of works under "Almaty - Khorgos" section within South-West Roads Project: Western Europe – Western China International Transit Corridor (CAREC 1b & 6b)
News
Printer-friendly versionPrinter-friendly version
09/30/2013 
Commencement of works under "Almaty - Khorgos" section within South-West Roads Project: Western Europe – Western China International Transit Corridor (CAREC 1b & 6b)

"Almaty - Khorgos" cement concrete road consists of eight sections (see table below). The total length of the road is 305 km. The construction period of each lot is 30 months.

The works under reconstruction of this road is financed jointly by the World Bank Loan No. 8156-KZ dated October 10, 2012, the Loan Agreement under which was ratified in May 23, 2013, as well as by the Budget of the Republic of Kazakhstan.

According to the results of the tender, the following Contractors and Consultants were assigned to the project execution.

Lot No.

Length

Name of the Contractors

Name of the Construction Supervision Consultants

1

km 0-50

Dogus Insaat Ve Ticaret A.S. & Gulsan Insaat Sanayi Turism Nakliyat Ve Ticaret A.S. (Turkey) (Lot 1 & 2)

Donsung Engineering Co. Ltd./ Dong Myeong Engineering Consultants & Architecture Co. Ltd./ «Zhol Sapa» LLP (Korea/Kazakhstan) (Lot 1-3)

2

km 50-111,7

3

km 111,7-171,1

 

JV Todini – Impregilo – KazakhDorStroy (Italy/Kazakhstan)  
 (Lot 3-6)

4

km 171,1-214,3

Sweroad/Gauff Ingenieure Gmbh/ТОО «Quality Planning Engineers & Consultanting» (Sweden/Kazakhstan) (Lot 4-6)

5

km 214,3-259,30

6

km 259,30-304,4

7

Bridges and overpasses at
km 214,3-304,4

JV «Evrascon» – «МО-1» (Azerbaijan/Kazakhstan) (Lot 7)

Donsung Engineering Co. Ltd./ Dong Myeong Engineering Consultants & Architecture Co. Ltd./ «Zhol Sapa» LLP (Korea/Kazakhstan) (Lot 7 & 8)

8

Bridge Ili (km 283)

OHL ZS (Czech Republic) (Lot 8)

At present the Contracts with all Contractors and Supervision Consultants have already been signed and they have started moblisation of personnel and equipment.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 