08/31/2015 
Work progress under remaining section in Kyzylorda region

Contractor "Euro-Asian Construction Corporation «EVRASCON» JSC is involved in implementation of the remaining section km 1702-1752 (length 49 km) in Kyzylorda region.

In general, earthworks, works under subbase, lower layer of the base course, binding course and wearing course are performed for 100%.

However, there are significant delays under following types of work:

- The top layer of crushed stone mastic asphalt concrete is constructed only on 14.4 km, ie, 29%;

- Culverts from the beginning of the year are performed in 3.2 pcs. (94%);

- Bridges are performed for 80%;

- Strengthening of shoulders, guardrails, road markings and sand depot are done 0%;

The reasons for delays are lack of funds, partial disorder of mobilized road-building machinery and equipment (crusher, ACP), partial lack of fuel, stabilizer for CSMA, unresolved issue of road-building materials from the former Contractor "Impresa" and absence of concluded contract for supply of geogrid, biomat, mineral powder, guardrails.

Machinery is mobilized in total 152 units out of the planned 101 units, it is required additionally 18 units.

All major road work is scheduled for completion by the end of this year and to open the main road for traffic but without shoulder protection and with speed limit to 60-70 km/hour. Works on road furniture is planned to complete in 2016.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts