Question №377
June 24, 2015
Temurlan Turdalin | Taraz

How do you do!
Could you please tell me how many years is the guarantee period of WE-WC road sections operation under categories (according to pavement material) - concrete, asphalt concrete, asphalt pavement – i.e. operation term before the first repair which as I understand, had to be approved prior to construction?
Second question: on one of the questions asked here (question No. 325 dated September 22, 2014) about construction of a tunnel on the border of Zhambyl region and SKO (near the village of Shakpakbaba), you answered that it will be located near Shakpakbaba settlement with the length of 800m at km 600 - 601. Where exactly this tunnel will be located - bypassing the village of Shakpakbaba, from the village of Shakpakbaba towards SKO or Zhambyl region? Has the construction commenced already?
Thank you in advance.             

Answer to question №377
July 3, 2015

Dear Temurlan, the defects liability period under WE-WC project provided by the Contractor is 2 years. In general the term of road operation according to requirements of SNiP makes 20 years, with performance of period between repairs (each 5 years medium repair, major repairs in 15 years after road commissioning).

The tunnel is on Shakpakbaba bypass on the left side if to go towards Zhambyl region. Construction was commenced last year and it is planned to complete at the end of 2015.

 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 

Стратегия 2050

 

 

 

 

"WE-WC" projects
“Nurly zhol” projects
Procurements
Announcements
Press center
Multimedia
Questions & Answers Contacts