02/09/2012 
The works for procurement of building materials for the forthcoming construction season for road section “Aktobe – Martuk – Border of RF” of Transit Corridor “Western Europe – Western China” are executed in accordance with time schedule
02/08/2012 
For Kyzylorda section of the constructed Transit Corridor “Western Europe – Western China” till the beginning of the current year 16 479 Kazakhstan people have been provided with working places, including 9 621 local people
02/01/2012 
The main subject for Public Hearings, conducted in five rayons of Almaty Oblast, was the discussion of Environmental Impact Assessment for the Project “Almaty – Khorgos”, approved by the World Bank
02/01/2012 
The results of development for transport-communication complex of the Republic of Kazakhstan for 2011 and tasks for 2012 have been reviewed at the enlarged session of Board
12/29/2011 
Overall 6 land plots are remaining for acquisition in the coming 2012 year for road section “Almaty – Khorgos” of International Transit Corridor “Western Europe – Western China”.
12/13/2011 
Hot crushed stone mastic mixes (CSMA) are applied in construction of the highway of international importance “Western Europe – Western China” while arrangement of upper courses of pavements, providing non-defective passage of heavy traffic.
12/12/2011 
The meeting “About progress of implementation for the Project “Western Europe – Western China” in South-Kazakhstan Oblast” has been conducted under the chair of Berik Kamaliev, Minister of Transport and Communications of the RK.
12/10/2011 
Berik Kamaliev, Minister of Transport and Communications of the RK, has conducted the meeting regarding implementation of Project “Western Europe – Western China” in Taraz city of Zhambyl Oblast.
12/08/2011 
Serious backlogs behind the time schedule can be observed during constr5uction works for Lots 6 and 8 in Kyzylorda Oblast, executed by Azerbaijan-Turkish Company “Akkord-Okan”.
11/25/2011 
Head of Transport Department, B. Kamaliev, instructed Contractors, working in Zhambyl Oblast, to provide overall disbursement of funds and completion of all the scope of works in accordance with time schedule.
 Navigation
 

 

 

«The completion of the Kazakhstan’s section of the Western Europe – Western China International Road Corridor is very important. It is really the construction of the century»

«We set an objective to develop infrastructure. And it turned out to be within our power. We are currently reviving the New Silk Road. We have opened access to the countries of the Persian Gulf and the Greater East. We have opened the Eastern gates, paving the way to the markets of China and the entire Asian continent», "Kazakhstan-2050” Strategy.
 
 
Address of the First President of the Republic of Kazakhstan – Elbasy, 2012.

 

 

 

 

«The executive authorities need a complete, high-quality Nurly Zhol Program. This is a strategic project which will affect the entire transport infrastructure».

 

 

 

 

 